Create a common task
- Go to the Common tasks (PM208030) window.
- Click .
-
In the Task ID field, enter an ID for the common task you want to create. This can be a ten-character string of letters and numbers.
- In the Description field, enter a description for the common task.
- On the General settings tab, in the Rate table field, select a rate table.
- Select an Invoicing option.
- Optional: When you add a common task, the settings for the Invoicing rule and Allocation rulewill be inherited from the project settings.
It is not necessary to set different rules, but if you do, the project settings will be overruled. - Optional: Fill in any other information you want to specify, on the other tabs.
- Click .
Related windows